After bringing electrical design to completion, building pre-production prototype, then production prototypes and getting ready for the pilot run, some of the critical parts just disappeared from the market. Well, not exactly disappeared, but lead time increased from 8 weeks to 4 months (I was still hopeful at that point), to 16 months! As we buy all electronic components from the US suppliers/distributors, looking Far East was not an option (too high a risk of getting countefeit parts). We have enough parts for a pilot run, and more, but not enough to secure steady production flow. In the end, it was a straightforward, yet difficult decision to put this product on ice.

I just felt like sharing my pain